a contactor hired 150 men to pave a road in 30 days.how many mem will be hire to do the same work in 20 days​

Respuesta :

kevinmario2008 kevinmario2008
  • 05-12-2021

Answer:375

Step-by-step explanation:W = RTN

1 = 1/7500(20)N

1 = 20/7500N

1 = 2/750N

750(1 = 2/750N)

750 = 2N

750/2 = N

375 = N

There are 375 men to do the job in 20 days

Answer Link

Otras preguntas

About how many books could a printing press produce i five month?
in the expression 2x + 3, the 2 is called _______.A) coefficient B) power C) product D) quotient
Please answer correctly for brainly
WILL MARK BRAINLIEST  A linear function has a slope of -7/9 and a y-intercept of 3. How does this function compare to the linear function that is represented b
What is the quotient 1074 divided by 26
How many legislative houses must agree to a dog specific legislation before can be sent to the president for his signature and become a law
I need help with Math please
Which group of ancient greek women had greater freedom slave women in athens free women athens or slave women in sparta or free women in sparta
Escucha la descripción del restaurante y responde a la siguientes pregunta. Click here for the audio. Escoge todas las frases ciertas. El restaurante tiene bue
Write an equation of the line passing through each of the following pairs of points. c (4, 0), (−2, 8)