8 students take 18 hours to construct a raft.
If the raft needs to be completed 12 hours earlier, calculate how many more students are needed.

Respuesta :

devishri1977
devishri1977 devishri1977
  • 04-08-2021

Answer:

16

Step-by-step explanation:

Students                      8       x

Time taken (hours)     18     18 - 12 = 6

If number of students increases, the work will completed in less hours.

So inverse proportion

[tex]x =\frac{18*8}{6}=3*8 = 24[/tex]

Additional students required = 24 - 8 = 16

Answer Link

Otras preguntas

what is a transfer of food goods and disease between the old new worlds columbian
Use patterns of zeros to find 5600÷7 show your work.
5\7m-2-6\7m=-13 what is the answer
What are the five seas that are apart of Asia ?
Jerome is writing a number in scientific notation. The number is greater than one million and less than ten million. What will be the exponent in the number Jer
Which one of the following sentences contains two ideas joined by a connecting word? A. Sally lives with her parents, although she could afford her own ap
what is 38% of 250? show your wor
The highest tier in cell hierarchy is _____.
Compare and contrast chinese and European means and motives for commercial expansion
Around the year 1000, Songhai’s leader converted to _____________________________, but most of the people continued to worship ________________________________.