if 9 people can do a piece of work in 90 days then how many days 19 people will take to complete the same piece of work​

Respuesta :

rmroomi2
rmroomi2 rmroomi2
  • 01-03-2021

Answer:

190 days

Step-by-step explanation:

cross multiply

19×90=1710

1710/9=190

Answer Link

Otras preguntas

What area of the long bone is covered with cartilage
What area of the long bone is covered with cartilage
which state capital is north of 40 degrees north latitude: Frankfort, denver, salt lake city, or columbus?
What what handels full name
What Is the Function of Alliteration in Literature?
write the equation in function form.then graph the equation x-3y=-9 ???
write the equation in function form then graph it 5x-2y=6 thx to the ppl who help
He believed that while there is serious unemployment in our auto industry, we should not ________ foreign cars. (A) build (B) repair (C) review (D) import (E) c
solve for m (r=3m+3z) solution is m=___, use integers or fractions for any numbers in the expression (simplify answer) please help
What area of the long bone is covered with cartilage