A critical activity is________________.a. an activity that consumes no time but shows precedence between events. b. a milestone accomplishment within the project. c. an activity with zero slack. d/ the beginning of an event.

Respuesta :

Ritmeks
Ritmeks Ritmeks
  • 09-03-2020

Answer:

C

Explanation:

Critical activity is the sequential activities from beginning to the end of a project. A lot of projects have a single critical path, although some projects may have more than one critical activity which depends on the flow logic utilized in the project.

Answer Link

Otras preguntas

What does "interpret the meaning of the quotient in terms of the two fractions given" mean?
If triangle GHI is similar to triangle JKL, which statement is true about the two triangles? Segment HI is proportional to segment KL, and angles G and K are p
A speed does not involve the element of
dr reilly has a patient who asks her about atherosclerosis
which best describes the colonists attitude toward american indians
which type of energy drives water cycle
A domestic cat can run at speeds of 27.5 miles per hour when chasing prey . A cheetah can run 42.5miles per hour faster when chasing prey. How fast can the chee
a construction company loads bricks weighing 12 pounds each on a pallet weighing 6 pounds which expression gives the weight of a pallet containing n bricks?
................................find 8% of 2.36.
200 meters, 19 seconds round to the nearest tenth